Worked Example

750 kN double-cover splice: separate capacity and spacing (Double-cover Splice)

Task: Follow the lecturer's trial sequence for bolt count and bearing, then identify why transverse spacing must change.

Original question · Lecture notes Chapter 2, p. 45–46 (Tutorial 2 Q1)
Original question with the given values boxed
Yellow boxes: values the question gives, the same values marked yellow in the Given table below.

The question in short: Two main plates, 150 mm wide and 22 mm thick, are joined end to end by two 12 mm cover plates with 6 M24 bolts at each end. The ultimate pull is 750 kN. Decide whether the bolts, plate bearing and main plate are adequate, and whether the hole spacing meets the rules.

What differs from the previous example of this type: Compared with the previous example: each bolt passes through the main plate and two cover plates, so it is in double shear; the load is already ultimate, so no load factor is applied; hole spacing is also checked.

GivenValue and Unit
Main/cover platesMain plate 150 mm wide, 22 mm thick; two cover plates, 12 mm each; S355 plates
BoltsSix M24 bolts at each end, 26 mm holes, Grade 8.8; As=353 mm2\htmlClass{read}{A_s=353\ \mathrm{mm^{2}}}
Loading750 kN, already ultimate tension
GeometryLongitudinal pitch 60 mm; end distance 40 mm; transverse spacing 70 mm
Strengthskbs=1.0\htmlClass{read}{k_{bs}=1.0}; ps=375\htmlClass{read}{p_s=375}, pbb=1000\htmlClass{read}{p_{bb}=1000}, pbs=550\htmlClass{read}{p_{bs}=550}, Us=510\htmlClass{read}{U_s=510}, Ub=800 N/mm2\htmlClass{read}{U_b=800\ \mathrm{N/mm^{2}}}

Yellow: values given in the question. The same values are marked where they are substituted in the steps below.
Orange box: values read directly from the Data File, the same values boxed orange in the lookup screenshots. A value interpolated between two table rows is a calculation, so it has no box.

Double-cover splice: side viewEach half transfers the full axial force; each bolt has two shear planes
Supplementary schematic for understanding; not to scale.

Solution Route: Identify double shear; find governing bolt/plate bearing PbsP_{bs}; estimate bolt count from resistance; finally check the arrangement.

Interactive 3D model · drag to turn

This browser cannot show the 3D model.

The main plates sit between two cover plates, so each bolt passes through three plates and has two shear planes (double shear). The force passes from the left main plate through the bolts into the covers and on to the right main plate; bearing is governed by the 22 mm main plate (the two covers total 24 mm).Yellow: values given in the question; orange box: values read from the Data File; white: calculated results; red arrows: forces.
Load path · the stations the force passes through, in order

The 750 kN passes from the left main plate through the bolts into the two cover plates, then through the bolts on the other side into the right main plate. The two halves are in series, so each half carries the full 750 kN.

  1. Ultimate tension
    750 kN (already an ultimate load)
    Step 1
  2. Main plate in tension (net section)
    Demand 750 kNCapacity 818.2 kN
    Utilisation 0.92 · closest to the limit
    Step 11–13
  3. Bearing on the main plate (6 bolts)
    Demand 750 kNCapacity 1452 kN
    Utilisation 0.52
    Step 3–7
  4. Bolts in double shear
    Capacity 264.75 kN per bolt, more than the 242 kN in plate bearing, so it does not govern
    Step 2–6
  5. Two cover plates
    Each takes half; together 24 mm, thicker than the 22 mm main plate
    Step 3
  6. Other half of the joint
    The same six bolts return the force to the right main plate
    Step 1
Red frame: the station closest to its limit. Each station links to the step that calculates it. Press “Show on the 3D model” to light up that part of the model above; press again to clear.
  1. Step 1 · Do not factor again

    Why this step: An ultimate load already includes the load factors; applying them again would overstate the demand. All later checks use this force directly.

    750 kN is ultimate load. The whole force passes successively through the left half-joint, covers and right half-joint.

    ▶ The lecturer on this part: 19 September 02:19:08

  2. Step 2 · Double-shear resistance per bolt

    Why this step: The main plate sits between two covers, so the bolt must be cut at two faces at once to fail. Its capacity is therefore twice that of single shear.

    Each bolt has two shear planes, hence ×2. This factor does not represent the two half-joints.

    New symbols in this step
    • PsP_s, PbbP_{bb}, PbsP_{bs}, PtP_t: Shear, bolt bearing, plate bearing and plate tension resistances; kN
    • psp_s, pbbp_{bb}, pbsp_{bs}, pyp_y: Corresponding course design strengths; N/mm²
    Ps=2psAs=2(375)(353)/1000=264.75 kNP_s=2p_sA_s=2({\htmlClass{read}{375}})({\htmlClass{read}{353}})/1000=264.75\ \mathrm{kN}
    Ps=2psAs=2(375)(353)/1000=264.75 kN\begin{aligned}P_s&=2p_sA_s\\&=2({\htmlClass{read}{375}})({\htmlClass{read}{353}})/1000\\&=264.75\ \mathrm{kN}\end{aligned}

    Units: psp_s in N/mm² times AsA_s in mm² gives N, then times the number of shear planes; dividing by 1000 gives kN.

    Data file lookup · Data Page 4 · Bolt tables
    The M24 row gives tensile stress area As = 353 mm²; the Grade 8.8 row gives ps = 375 N/mm² and pbb = 1000 N/mm².
    The M24 row gives tensile stress area As=353 mm2A_s=353\ \mathrm{mm^{2}}; the Grade 8.8 row gives ps=375 N/mm2p_s=375\ \mathrm{N/mm^{2}} and pbb=1000 N/mm2p_{bb}=1000\ \mathrm{N/mm^{2}}.Yellow: given parameter, row or columnOrange: value read from the table, boxed orange in the text too

    ▶ The lecturer on this part: 19 September 02:24:49

  3. Step 3 · Select bearing thickness

    Why this step: The main plate pulls one way and the two covers together pull the other way. The thinner side gives the bolt less contact area, so the bolt is more likely to be crushed there.

    Compare the 22 mm main plate with combined covers of 24 mm and use 22 mm. Substitute d=24 mmd=24\ \mathrm{mm} for M24 and tp=22 mmt_p=22\ \mathrm{mm}.

    Pbb=d tp pbb=24(22)(1000)/1000=528 kNP_{bb}=d\,t_p\,p_{bb}={\htmlClass{given}{24}}({\htmlClass{given}{22}})({\htmlClass{read}{1000}})/1000=528\ \mathrm{kN}
    Pbb=d tp pbb=24(22)(1000)/1000=528 kN\begin{aligned}P_{bb}&=d\,t_p\,p_{bb}\\&={\htmlClass{given}{24}}({\htmlClass{given}{22}})({\htmlClass{read}{1000}})/1000\\&=528\ \mathrm{kN}\end{aligned}

    Units: dd and tpt_p are in mm and pbbp_{bb} is in N/mm², so the product is in N; dividing by 1000 gives kN.

  4. Step 4 · Calculate clear spacing first

    Why this step: When the bolt pushes on the hole wall, what must tear is the steel left between two holes, not the full centre-to-centre length.

    60 mm is hole-centre spacing; clear spacing is 60−26.

    New symbols in this step
    • dd, d0d_0, ee, lel_e: Bolt diameter, hole diameter, end distance along force and clear hole spacing; mm
    • pp, nn: Bolt spacing along the force, mm; number of bolts
    le=p−d0=60−26=34 mml_e=p-d_0={\htmlClass{given}{60}}-{\htmlClass{given}{26}}=34\ \mathrm{mm}

    ▶ The lecturer on this part: 19 September 02:33:48

  5. Step 5 · Calculate plate-bearing bounds individually

    Why this step: This guards against the main plate being crushed or torn near the bolt holes. Whichever value is smallest is the way the plate would fail first.

    Standard holes use kbs=1k_{bs}=1. The four values correspond to hole-wall bearing, end distance ee, clear hole spacing and the upper cap.

    New symbols in this step
    • kbsk_{bs}, KeK_e: Hole-type and effective-area factors; dimensionless
    kbsdtppbs=1.0(24)(22)(550)/1000=290.40.5kbsetppbs=0.5(1.0)(40)(22)(550)/1000=2421.5letpUs=1.5(34)(22)(510)/1000=572.222.0dtpUb=2.0(24)(22)(800)/1000=844.8Pbs=min⁡(290.4, 242, 572.22, 844.8)=242 kN\begin{aligned}k_{bs}dt_pp_{bs}&={\htmlClass{read}{1.0}}({\htmlClass{given}{24}})({\htmlClass{given}{22}})({\htmlClass{read}{550}})/1000=290.4\\0.5k_{bs}et_pp_{bs}&=0.5({\htmlClass{read}{1.0}})({\htmlClass{given}{40}})({\htmlClass{given}{22}})({\htmlClass{read}{550}})/1000=242\\1.5l_et_pU_s&=1.5(34)({\htmlClass{given}{22}})({\htmlClass{read}{510}})/1000=572.22\\2.0dt_pU_b&=2.0({\htmlClass{given}{24}})({\htmlClass{given}{22}})({\htmlClass{read}{800}})/1000=844.8\\P_{bs}&=\min(290.4,\ 242,\ 572.22,\ 844.8)=242\ \mathrm{kN}\end{aligned}
    kbsdtppbs=1.0(24)(22)(550)/1000=290.40.5kbsetppbs=0.5(1.0)(40)(22)(550)/1000=2421.5letpUs=1.5(34)(22)(510)/1000=572.222.0dtpUb=2.0(24)(22)(800)/1000=844.8Pbs=min⁡(290.4, 242, 572.22, 844.8)=242 kN\begin{aligned}k_{bs}dt_pp_{bs}&={\htmlClass{read}{1.0}}({\htmlClass{given}{24}})({\htmlClass{given}{22}})({\htmlClass{read}{550}})/1000\\&=290.4\\0.5k_{bs}et_pp_{bs}&=0.5({\htmlClass{read}{1.0}})({\htmlClass{given}{40}})({\htmlClass{given}{22}})({\htmlClass{read}{550}})/1000\\&=242\\1.5l_et_pU_s&=1.5(34)({\htmlClass{given}{22}})({\htmlClass{read}{510}})/1000\\&=572.22\\2.0dt_pU_b&=2.0({\htmlClass{given}{24}})({\htmlClass{given}{22}})({\htmlClass{read}{800}})/1000\\&=844.8\\P_{bs}&=\min(290.4,\ 242,\ 572.22,\ 844.8)\\&=242\ \mathrm{kN}\end{aligned}

    Where the numbers come from: 3434 from Step 4.

    Units: All lengths and the thickness are in mm; pbsp_{bs}, UsU_s and UbU_b are in N/mm². Each product is in N, and dividing by 1000 gives kN.

    Data file lookup · Data Page 4 · Bearing of connected part
    Standard holes give kbs = 1.0. For S355 plate the bearing strength is pbs = 550 N/mm² and Us = 510 N/mm²; for the bolt Ub = 800 N/mm².
    Standard holes give kbs=1.0k_{bs}=1.0. For S355 plate the bearing strength is pbs=550 N/mm2p_{bs}=550\ \mathrm{N/mm^{2}} and Us=510 N/mm2U_s=510\ \mathrm{N/mm^{2}}; for the bolt Ub=800 N/mm2U_b=800\ \mathrm{N/mm^{2}}.Yellow: given parameter, row or columnOrange: value read from the table, boxed orange in the text too
    Load path · Four limits on plate bearing
    Bolt pushes towards the plate end →d = 24Hole wall crusheskbsdtppbs​= 290.4 kNe = 40End tear-out0.5kbsetppbs​= 242 kNGoverns (smallest)le​ = 34Tear between holes1.5letpUs​= 572.22 kNUb​Bolt strength cap2.0dtpUb​= 844.8 kNSix bolts: 6 × 242 = 1452 kN > 750 kN
    The bolt presses on the hole wall, and the plate can fail in four ways: the hole wall crushes, the bolt tears out through the plate end, the plate tears between two holes, and there is a cap set by the bolt strength. The smallest of the four values is used (red frame).
  6. Step 6 · Identify the governing mode

    Why this step: The force each bolt can pass on is set by the weakest item. Dividing the total pull by it gives the least number of bolts needed.

    Per bolt: shear 264.75, bolt bearing Pbb=528P_{bb}=528 and plate bearing Pbs=242P_{bs}=242. Use 242 for this comparison.

    New symbols in this step
    • FF, FsF_s, FTF_T: Total force, shear per bolt and tension per bolt; kN
    nreq=F/Pbs=750/242≈3.10n_{req}=F/P_{bs}={\htmlClass{given}{750}}/242\approx3.10

    Where the numbers come from: 242242 from Step 5.

    ▶ The lecturer on this part: 19 September 02:39:25

  7. Step 7 · Integer bolt count and the given layout

    Why this step: A bolt count cannot be a fraction, so it is rounded up. The actual number on the drawing times the capacity per bolt is then confirmed to exceed the pull.

    Resistance alone requires at least four bolts. The lecturer retains six per half-joint as drawn. This does not authorise simply deleting two, because layout and other checks would also change.

    nPbs=6(242)=1452 kN>F=750 kNnP_{bs}={\htmlClass{given}{6}}(242)=1452\ \mathrm{kN}>F={\htmlClass{given}{750}}\ \mathrm{kN}
    nPbs=6(242)=1452 kN>F=750 kN\begin{aligned}nP_{bs}&={\htmlClass{given}{6}}(242)\\&=1452\ \mathrm{kN}\\&>F\\&={\htmlClass{given}{750}}\ \mathrm{kN}\end{aligned}

    Where the numbers come from: 242242 from Step 5.

  8. Step 8 · Longitudinal pitch check

    Why this step: Holes too close leave little steel between them and make fitting awkward. Holes too far apart may let the plates gape between bolts. So spacing has a lower and an upper limit.

    Minimum 2.5d=60 mm2.5d=60\ \mathrm{mm} equals the provided 60 mm. Maximum min⁡(12t, 150)\min(12t,\,150) is 144 mm for a 12 mm cover; 60 mm is also below it.

    2.5d=2.5(24)=60 mm,min⁡(12t, 150)=min⁡(12(12), 150)=144 mm2.5d=2.5({\htmlClass{given}{24}})=60\ \mathrm{mm},\qquad\min(12t,\ 150)=\min({\htmlClass{given}{12}}({\htmlClass{given}{12}}),\ 150)=144\ \mathrm{mm}
    2.5d=2.5(24)=60 mmmin⁡(12t, 150)=min⁡(12(12), 150)=144 mm\begin{aligned}2.5d&=2.5({\htmlClass{given}{24}})=60\ \mathrm{mm}\\\min(12t,\ 150)&=\min({\htmlClass{given}{12}}({\htmlClass{given}{12}}),\ 150)\\&=144\ \mathrm{mm}\end{aligned}
  9. Step 9 · Transverse spacing still fails

    Why this step: Enough capacity does not make the layout acceptable. Holes too close across the force also leave too little steel between them, so the spacing is increased.

    The course requires at least 3d=72 mm3d=72\ \mathrm{mm} perpendicular to the force. The shown 70 mm is insufficient; the lecturer changes it to 75 mm.

    70 mm<3d=3(24)=72 mm{\htmlClass{given}{70}}\ \mathrm{mm}<3d=3({\htmlClass{given}{24}})=72\ \mathrm{mm}
  10. Step 10 · Review the drawing after revision

    Why this step: The plate width stays the same, so moving the holes apart leaves less steel between hole and plate edge. Too small an edge distance can let the edge tear, so the layout is looked at again.

    Changing spacing affects edge distances, plate width or clear distances. Recheck the actual arrangement; changing one displayed number does not complete the design.

  11. Step 11 · Main-plate net section

    Why this step: This guards against the main plate being pulled apart along a row of holes. Two holes remove steel at this section, making it the weakest place in the plate.

    The main plate is thinner than the combined covers, 22<24 mm, so it is checked here. Deduct two 26 mm holes from the 150 mm width.

    New symbols in this step
    • AsA_s, AgA_g, AnA_n, AeA_e: Bolt effective shear area and gross/net/effective plate areas; mm²
    An=(b−2d0)t=(150−2×26)(22)=2156 mm2A_n=(b-2d_0)t=({\htmlClass{given}{150}}-2\times{\htmlClass{given}{26}})({\htmlClass{given}{22}})=2156\ \mathrm{mm^2}
    An=(b−2d0)t=(150−2×26)(22)=2156 mm2\begin{aligned}A_n&=(b-2d_0)t\\&=({\htmlClass{given}{150}}-2\times{\htmlClass{given}{26}})({\htmlClass{given}{22}})\\&=2156\ \mathrm{mm^2}\end{aligned}

    ▶ The lecturer on this part: 19 September 02:57:53

  12. Step 12 · Effective area

    Why this step: The section through the holes is only a short length, and steel there can develop a little more than pyp_y. KeK_e raises the net area slightly to allow for this.

    Apply Ke=1.1K_e=1.1, capped at gross area Ag=150×22=3300 mm2A_g=150\times22=3300\ \mathrm{mm^{2}}.

    Ag=bt=150(22)=3300 mm2Ae=KeAn=1.1(2156)=2371.6<Ag=3300 mm2\begin{aligned}A_g&=bt={\htmlClass{given}{150}}({\htmlClass{given}{22}})=3300\ \mathrm{mm^2}\\A_e&=K_eA_n={\htmlClass{read}{1.1}}(2156)=2371.6<A_g=3300\ \mathrm{mm^2}\end{aligned}
    Ag=bt=150(22)=3300 mm2Ae=KeAn=1.1(2156)=2371.6<Ag=3300 mm2\begin{aligned}A_g&=bt={\htmlClass{given}{150}}({\htmlClass{given}{22}})=3300\ \mathrm{mm^2}\\A_e&=K_eA_n\\&={\htmlClass{read}{1.1}}(2156)\\&=2371.6\\&<A_g\\&=3300\ \mathrm{mm^2}\end{aligned}

    Where the numbers come from: 21562156 from Step 11.

    Data file lookup · Data Page 2 · Tension members
    Ke = 1.1 for S355.
    Ke=1.1K_e=1.1 for S355.Yellow: given parameter, row or columnOrange: value read from the table, boxed orange in the text too
  13. Step 13 · Main-plate tension resistance

    Why this step: Area times strength gives the pull the main plate can take before it breaks at the holes. Since it exceeds the demand, the plate will not break.

    Use py=345 N/mm2p_y=345\ \mathrm{N/mm^{2}} for 22 mm thickness.

    Pt=pyAe=345(2371.6)/1000≈818.2 kN>750 kNP_t=p_yA_e={\htmlClass{read}{345}}(2371.6)/1000\approx818.2\ \mathrm{kN}>{\htmlClass{given}{750}}\ \mathrm{kN}
    Pt=pyAe=345(2371.6)/1000≈818.2 kN>750 kN\begin{aligned}P_t&=p_yA_e\\&={\htmlClass{read}{345}}(2371.6)/1000\\&\approx818.2\ \mathrm{kN}\\&>{\htmlClass{given}{750}}\ \mathrm{kN}\end{aligned}

    Where the numbers come from: 2371.62371.6 from Step 12.

    Units: pyp_y is in N/mm² and AeA_e is in mm², so the product is in N; dividing by 1000 gives kN.

    Data file lookup · Data Page 1 · Design strength pyp_y
    Main plate 22 mm thick: the T ≤ 40 mm row, S355 column gives py = 345 N/mm².
    Main plate 22 mm thick: the T≤40 mmT\le40\ \mathrm{mm} row, S355 column gives py=345 N/mm2p_y=345\ \mathrm{N/mm^{2}}. How the grade and thickness choose this row →Yellow: given parameter, row or columnOrange: value read from the table, boxed orange in the text too
Conclusion

This example distinguishes adequate resistance from compliant hole detailing. Main-plate net-section resistance 818.2 kN exceeds 750 kN, so main-plate tension is also adequate.

All the symbols of this example

SymbolsMeaning and Units
FF, FsF_s, FTF_TTotal force, shear per bolt and tension per bolt; kN
PsP_s, PbbP_{bb}, PbsP_{bs}, PtP_tShear, bolt bearing, plate bearing and plate tension resistances; kN
dd, d0d_0, ee, lel_eBolt diameter, hole diameter, end distance along force and clear hole spacing; mm
AsA_s, AgA_g, AnA_n, AeA_eBolt effective shear area and gross/net/effective plate areas; mm²
psp_s, pbbp_{bb}, pbsp_{bs}, pyp_yCorresponding course design strengths; N/mm²
UsU_s, UbU_bPlate and bolt ultimate tensile strengths; N/mm²
kbsk_{bs}, KeK_eHole-type and effective-area factors; dimensionless
pp, nnBolt spacing along the force, mm; number of bolts